B88IDO Case Studies


Isolation Drying and Off-Loading Project

Client: GlaxoSmithKline       Timeline:  6 month Duration       CE Role:  EPCM

Scope of the Project

The client required an improvement in their process for the Isolation, Drying and Off-Loading to Drums of a Potent Pharmaceutical product.

The plant improvements included a new crystallisor vessel, 1m2 Filter Dryer c/w Isolator and package units for Vacuum and Temperature Control.

Clark Eriksson's remit was for a Full EPCM Role including Validation for DQ, IQ and OQ.

Clark Eriksson provided and co-ordinated a full complement of specialist engineering design services, from readily available in-house resources, including process, mechanical, plant design, civil and structural, Instrument and Electrical as well as the necessary project and procurement support.

Scale of Project

The total installed cost of the project was £1,200,000.  Which involved installation of the main plant items into an existing structure.  All Piping in Hygienic SS, Instrumentation, Electrical and Civil works were undertaken by CEA appointed sub-contractors.  The project was completed within a 6 month period from Sanction to final handover to the client.